Title: SR 410-204th Ave Intersection
Category: City/Public
Address: 20637 WA-410, Bonney Lake, WA 98391, USA
Contact Person: City Engineer
Contact Number: (253) 447-4336

Status and Details:

Installation of a traffic signal at the intersection of 204th Avenue E and SR 410, per development agreements between the City of Bonney Lake and Weyerhaeuser Real Estate Development Co. / WSU / Visconsi.

See also:

Project Updates

View the Legal Notices page for notices and formal press releases.

Follow the City's official Blog, Facebook, or Twitter feeds to get quick updates and reports.
City Blog - 
Facebook - 
Twitter - Police Department - @BLPoliceDept / City - @CityBonneyLake

Project updates and staff reports are also available in the Mayor's Weekly Newsletter and the monthly Bonney Lake Reporter newsletter - view newsletters / sign up to receive newsletters

3/21/2018: The contractor for the SR410/204th intersection improvement project removed barriers; installed the remaining signal arms, and is preparing to install c-curbing on the east end next week.

204th final overlay of pavement should occur next week.

1/16/2018: The contractor is coordinating plans with WSDOT and Transportation Systems to begin signal change-out on Tuesday, January 23th. Message boards area placed on SR 410.

The Signal Change outs will be as follows from 9:00AM – 2:00PM:
Tuesday, January 23 :                192nd Ave E
Wednesday, January 24 :           195th Ave E
Thursday, January 25 :               198th Ave E

Tuesday, January 30 :                214TH  Ave E
Wednesday, January 31:            211th Ave E
Thursday, February 1:                208th Ave E


11/21/2017: Contractor is working with the City to address traffic control issues to move the work zone to construct the median islands on the SR 410/204th intersection improvements project.

Costco sewer and water main testing is underway.

11/9/2017: Contractor has completed construction of the new East bound lane, Installed Sidewalks, Landscaping, Street lights and Utilities along the Southerly shoulder of SR410 between South Prairie Rd and 208th Ave E.
Contractor will begin construction of the new Center Median Planter Strip this month. To do so, Traffic will be revised with two lanes in each direction around Concrete Barriers.
Signal poles for the new 204th Ave East Intersection will be installed by the end of November. Also, new Signal Control Cabinets will be installed at six existing intersections (192nd, 195th, 198th, 208th, 211th and 214th) in December to provide better signal communication and traffic flow along SR410 and the respective intersections. 
Traffic flow will continue around the Concrete Barriers throughout the winter until landscaping of the Center Median, Signal work and Final paving is complete.

9/23/2017: The contractor for the SR 410/204th intersection improvements completed water pressure and purity testing of the water main crossing of SR 410.

8/12/2017: The contractor for the SR 410/204th intersection improvements has relocated the median barriers for construction activities to allow traffic to move unimpeded.

8/1/2017: SR410 Night Road Work Scheduled August 1-3, 2017 - view details.

12/3/2016: City staff met with WSDOT and the developer to discuss comments and concerns about the plans and specifications submitted for review.