2019 Seal Coat Schedule Starting August 19, 2019

Northwest Traffic, Inc. will be starting the application of a seal coat for the City of Bonney Lake on Monday, August 19, 2019, with the intent to be completed prior to the start of the school year. Please see the attached schedule/maps depicting the dates this work will be done. The dates for this work will be dependent on dry weather. Please be aware that some streets will be partially seal coated on one day and completed on another day to allow for residents to park. Park on adjacent streets while this work is being performed. The newly seal coat roads need a drying time of 4 – 4 ½ hours. Contractor will remove all barricades and open the street to traffic upon the completion of the curing process.

If you have any questions or concerns, please contact Public Works at 253 447-4319.

Click this link for map and schedule.