Construction Plan for Myers Rd E – Updated 9-11-18 Anticipated Construction Schedule

Monday 9/24/18

7:00am – Set up traffic control to close Meyers Road from State Route 410 to 81st St E 7:30am – Remove guardrail

7:45am – Temporarily remove overhead distribution line and take outage on transmission line 8:00am – Mobilize equipment to site (low drill, baker tank, dump truck, crane, etc.)

9:00am – Begin drilling the North hole site

6:00pm – Demobilize but leave equipment onsite. Keep road blocks up to prevent thru-traffic

Tuesday 9/25/18

7:00am – Continue drilling the North hole site

7:30am – Replace existing wood pole just south of drilling site 6:00pm – Demobilize but leave equipment onsite.

 

Wednesday 9/26/18

7:00am – Continue drilling the North hole site 5:00pm – Finish drilling the North hole site 6:00pm – Demobilize but leave equipment onsite.

Thursday 9/27/18

7:00am – Prepare for concrete pour. 8:00am – Install rebar cage.

10:00am – Begin pouring concrete 4:00pm – Set anchor bolt cage 6:00pm – Finish concrete pier

Friday Day 9/28/18

7:00am – Clean-up site to make ready for thru-traffic

3:00pm – Install temporary jersey barriers in place of guardrail 4:00pm – Finish cleaning up site for thru-traffic

5:00pm – Open for thru-traffic

Saturday and Sunday:

Meyers Road will be open for thru-traffic

Monday 10/1/18

7:00am – Set up traffic control to close Meyers Road from State Route 410 to 81st St E

7:45am – Temporarily remove overhead distribution line and take outage on transmission line

8:00am – Mobilize equipment to site (low drill, baker tank, dump truck, crane, etc.) 9:00am – Begin drilling the South hole site

6:00pm – Demobilize but leave equipment onsite. Keep road blocks up to prevent thru-traffic

Tuesday 10/2/18

7:00am – Continue drilling the South hole site 6:00pm – Demobilize but leave equipment onsite.

Wednesday 10/3/18

7:00am – Continue drilling the South hole site 5:00pm – Finish drilling the South hole site 6:00pm – Demobilize but leave equipment onsite.

Thursday 10/4/18

7:00am – Prepare for concrete pour. 8:00am – Install rebar cage.

10:00am – Begin pouring concrete 4:00pm – Set anchor bolt cage 6:00pm – Finish concrete pier

Friday 10/5/18

7:00am – Clean-up site to make ready for thru-traffic

3:00pm – Install temporary jersey barriers in place of guardrail 4:00pm – Finish cleaning up site for thru-traffic

5:00pm – Open for thru-traffic

**We will be offsite for at least a week (maybe 2 weeks pending construction issues)

Monday 10/15/18

7:00am – Set up traffic control to close Meyers Road from State Route 410 to 81st St E

7:45am – Temporarily remove overhead distribution line and take outage on transmission line 8:00am – Mobilize equipment to site

9:00am – Begin stacking 1st steel pole 5:00pm – Finish stacking pole

6:00pm – Demobilize from site but leave equipment

Tuesday 10/16/18

7:00am – Begin stacking 2nd steel pole 5:00pm – Finish stacking pole

6:00pm – Demobilize from site but leave equipment Wednesday 10/17/18

7:00am – Begin pulling in new wire and transferring existing wire 6:00pm – Demobilize from site

Thursday 10/18/18

7:00am – Continue pulling in new wire and transferring existing wire 6:00pm – Finish the wire work

Friday 10/19/18

7:00am – Restore site and re-install the guardrail for thru-traffic

This entry was posted in Information. Bookmark the permalink.

One Response to Myers Road Closure

  1. kelly Bellisle says:

    is there not a way to just block one side of the road. there are apartments just past the stop sign and school buses use this route

Comments are closed.