SR 410 Impact: Night Road Work scheduled May 7-9, May 14-16

The city’s contractor will be working several nights (8pm to 6am) on SR 410 between South Prairie Road and 208th Avenue E in Bonney Lake.

The intersections of SR 410 & South Prairie Road and SR 410 & 208th Ave E will have uniformed Police Officers with vehicles to operate the intersections safely.

Expected work nights are as follows:

  • Grinding road surfaces: May 7, 8, and 9, 2018
  • Paving road surfaces: May 14, 15, and 16, 2018

The contractor will start presetting signs at 8:00 p.m. on the dates listed, and controlling the intersection by 9:00 p.m. Lanes will reopen at 6:00 a.m. the following morning.

Questions? Call 253-447-4336

 

For more information view the Project page:
http://www.ci.bonney-lake.wa.us/googlemaps/project_details.php?Project_ID=242

See also the Mountainview Marketplace/Costco Project page:
http://www.ci.bonney-lake.wa.us/googlemaps/project_details.php?Project_ID=235

 